Sefton Park Junction Infrastructure Upgrade


Transport for NSW acknowledges the Burramattagal people of the Darug Nation as the Traditional Custodians of the lands on which we work and pay respects to Elders past and present. We recognise & celebrate the diversity of Aboriginal peoples and their ongoing cultures & connections to the lands and waters of NSW.


The NSW Government is upgrading rail infrastructure at Sefton Park Junction as part of the More Trains, More Services program.

This program will simplify and modernise the rail network creating high capacity, turn up and go services for many customers. It means customers can expect more frequent train services, with less wait times, less crowding on a simpler and more reliable network.

We are carrying out electrical infrastructure upgrades and track modifications to improve train movements through Sefton Park Junction. We will be working within and adjacent to the rail corridor to complete this work.

Key benefits

These include:

  • removing, relocating and reconfiguring track and signalling infrastructure so trains can operate safely and efficiently
  • modify electrical assets and combined service routes, and upgrade overhead wiring and structures to support train operations
  • complete civil and structural activities to support corridor upgrades and train operations.

Project Status

A contract has been awarded to Transport for Tomorrow an alliance between Transport for NSW, Laing O’Rourke and KBR, to start early work for the Sefton Park Junction Infrastructure Upgrade project.

Early investigation work will start in September 2022 and include:

  • environment and safety site walks
  • 3D scanning to identify underground services
  • underline road crossing (ULX) identification
  • potholing for service routes
  • temporary site establishment.

Project map

Keeping our work sites safe

We are continuing to deliver projects across New South Wales while ensuring the safety of all staff and the community. All work will be carried out in line with current NSW Government Public Health Orders and Restrictions which are subject to change.

Keeping you up to date

We are committed to reducing environmental impacts and are starting to phase out the distribution of paper notifications.

Instead, we will be providing construction updates by email.

If you would like to be emailed project updates please contact us on 1800 684 490 or email projects@transport.nsw.gov.au.

If our work is anticipated to directly impact your property and we do not have your contact details, we will distribute a paper notification to your address to ensure you are aware of upcoming activities.

West of Bankstown rail services in 2024

As part of the integration of Sydney Metro City & Southwest, rail services on the T3 Bankstown Line will change for stations west of Bankstown.

Services currently operating between Liverpool and the City Circle via Bankstown will instead run via Regents Park and Lidcombe. A shuttle service will operate between Bankstown and Lidcombe, with Regents Park to become the main interchange point for customers switching between the two T3 Bankstown Line branches.

For more information on the planned service changes, please visit the website.

Station information

Sefton Park Junction is located between Sefton, Regents Park, and Birrong Stations.

Please visit the specific Station webpages for information on station facilities and transport services:


Transport for NSW acknowledges the Burramattagal people of the Darug Nation as the Traditional Custodians of the lands on which we work and pay respects to Elders past and present. We recognise & celebrate the diversity of Aboriginal peoples and their ongoing cultures & connections to the lands and waters of NSW.


The NSW Government is upgrading rail infrastructure at Sefton Park Junction as part of the More Trains, More Services program.

This program will simplify and modernise the rail network creating high capacity, turn up and go services for many customers. It means customers can expect more frequent train services, with less wait times, less crowding on a simpler and more reliable network.

We are carrying out electrical infrastructure upgrades and track modifications to improve train movements through Sefton Park Junction. We will be working within and adjacent to the rail corridor to complete this work.

Key benefits

These include:

  • removing, relocating and reconfiguring track and signalling infrastructure so trains can operate safely and efficiently
  • modify electrical assets and combined service routes, and upgrade overhead wiring and structures to support train operations
  • complete civil and structural activities to support corridor upgrades and train operations.

Project Status

A contract has been awarded to Transport for Tomorrow an alliance between Transport for NSW, Laing O’Rourke and KBR, to start early work for the Sefton Park Junction Infrastructure Upgrade project.

Early investigation work will start in September 2022 and include:

  • environment and safety site walks
  • 3D scanning to identify underground services
  • underline road crossing (ULX) identification
  • potholing for service routes
  • temporary site establishment.

Project map

Keeping our work sites safe

We are continuing to deliver projects across New South Wales while ensuring the safety of all staff and the community. All work will be carried out in line with current NSW Government Public Health Orders and Restrictions which are subject to change.

Keeping you up to date

We are committed to reducing environmental impacts and are starting to phase out the distribution of paper notifications.

Instead, we will be providing construction updates by email.

If you would like to be emailed project updates please contact us on 1800 684 490 or email projects@transport.nsw.gov.au.

If our work is anticipated to directly impact your property and we do not have your contact details, we will distribute a paper notification to your address to ensure you are aware of upcoming activities.

West of Bankstown rail services in 2024

As part of the integration of Sydney Metro City & Southwest, rail services on the T3 Bankstown Line will change for stations west of Bankstown.

Services currently operating between Liverpool and the City Circle via Bankstown will instead run via Regents Park and Lidcombe. A shuttle service will operate between Bankstown and Lidcombe, with Regents Park to become the main interchange point for customers switching between the two T3 Bankstown Line branches.

For more information on the planned service changes, please visit the website.

Station information

Sefton Park Junction is located between Sefton, Regents Park, and Birrong Stations.

Please visit the specific Station webpages for information on station facilities and transport services:

  • We are always exploring ways to better connect with the communities while minimising impacts on the environment. To help us reduce paper waste, please complete this brief survey and let us know if you would prefer receive out updates to your inbox instead of you mailbox.